Enter Project Budget Changes

Prerequisites


The following steps assume you have already enabled the control change log and you want to process project level changes to the project's negotiated cost (NC), enter a value for authorized unpriced work (AUW), or make other contract budget base adjustments to undistributed budget (UB) or management reserve (MR).


What to Do Next

  • You may want to produce a budget change log report to verify your transactions. In the Run By report option, select Project when you want to review just the project level changes, select Account when you want to review the control account and subordinate work package changes, or select All to review the project level and control account level changes.