Enter Project Budget Changes
Prerequisites
- Set the Project Budget Base. This includes the contract total cost value, budget baseline value, and budget set aside as management reserve.
- Enable the Change Control Log.
The following steps assume you have already enabled the control change log and you want to process project level changes to the project's negotiated cost (NC), enter a value for authorized unpriced work (AUW), or make other contract budget base adjustments to undistributed budget (UB) or management reserve (MR).
- Select . The Manage Projects tab window displays.
- Click on the dropdown in the Ribbon Menu and select the project you want from the list.
- Select the Change Control tab.
- Click on the dropdown in the lower right of the tab.
- Select . The Project Adjustment dialog box displays.
- When applicable, in the dropdown, select the account you want to decrease the budget amount. In some instances, you may want to accept the default setting of . For example, you would leave this set to None when you are increasing the authorized unpriced work. You have two other options for this dropdown - select either Authorized Unpriced Work or Negotiated Cost.
- In the dropdown, select the account you want to increase the budget amount. For example, when there is a contract modification that increases the authorized unpriced work, select the applicable account. You have three options for this dropdown: None, Authorized Unpriced Work, or Negotiated Cost. In some instances, you may want to accept the default setting of None when you are processing a debit transaction to either Authorized Unpriced Work or Negotiated Cost.
-
When you have selected Authorized Unpriced Work in Step 7, the dropdown is enabled. Use this option to also credit either Undistributed Budget or Management Reserve the same amount - these are the only two options for the dropdown.
Tip:
All changes to the negotiated cost should be processed through the authorized unpriced work account. Begin with a credit to authorized unpriced work and undistributed budget or management reserve to keep the contract budget base numbers in balance. Once the work effort has been negotiated with the customer, you would debit the authorized unpriced work account and credit the negotiated cost account.
- Enter the budget for the transaction. This could be a debit value, credit value, or transfer between accounts.
- For the , you can accept the auto generated number or enter a user defined reference number.
- Enter notes in the section in the dialog box to document why you made the transfer.
- Click in the Ribbon Menu. The account values are updated in the Change Control tab.
- Optional. Close the Manage Projects tab.
- Select . The Manage Projects tab window displays.
- Click on the dropdown in the Ribbon Menu and select the project you want from the list.
- Select the Change Control tab.
- Click on the dropdown in the lower right of the tab.
- Select . The Project Adjustment dialog box displays.
- In the dropdown, select the account you want to transfer budget from. For example, if you want to move budget from Undistributed Budget, select that account. The budget for the account also displays in the dialog box so you know the amount available to transfer.
- In the dropdown, select the account you want to transfer budget to. For example, if you selected Undistributed Budget in Step 6, you would select Management Reserve.
- Enter the you want to transfer between the accounts.
- For the , you can accept the auto generated number or enter a user defined reference number.
- Enter notes in the section in the dialog box to document why you made the transfer.
- Click in the Ribbon Menu. The account values are updated in the Change Control tab.
- Optional. Close the Manage Projects tab.
What to Do Next
- You may want to produce a budget change log report to verify your transactions. In the report option, select when you want to review just the project level changes, select when you want to review the control account and subordinate work package changes, or select to review the project level and control account level changes.